Sandfire Resources’ (Sandfire) DeGrussa copper comminution circuit has been designed to produce, by today’s standards, a very fine primary grind size of 45 microns. The grinding circuit is comprised of two stages of milling – primary and secondary, to process 1.5Mt per annum (187tph) of primary sulphide ore. The primary grinding circuit consists of a 7.30m x 3.35m variable speed SAG mill in closed circuit with 500mm cyclones designed to deliver a 180m transfer size, the secondary grinding circuit consists of a 4.7m x 7.5m ball mill in closed circuit with 250mm cyclones to provide a 45m product to flotation.
Initially the primary mill was commissioned as an autogenous grinding mill (AG mill) at lower than designed throughput (~150tph) and to achieve the design capacity of 187tph steel grinding media was added. Even with the steel addition, high pebble generation with finer transfer size (<100µm) and excessively fine flotation feed have remained an issue. The over-ground sulfides in the flotation feed led to issues in maintaining mineral selectivity and optimised copper recovery.
Several process and operational changes were carried out to reduce the circulation of critical size material and generation of ultra-fines, however stable throughput rates could not be maintained at the design rate of 187tph. Besides the process issues, the variable speed drive (Slip Energy Recovery - SER) limited the available power to the system to ensure the driveline was not over loaded, and the mill vibration at higher mill speeds limited the upper operating range to 74% critical speed. Further to these issues it became difficult to maintain a high ball charge in the SAG mill, to maintain throughput, due to concern over damaging the grates and shell liners (pushing the mill to the design boundaries) .
This paper discusses the journey from discovery through comminution design and into commissioning of the DeGrussa concentrator, the difficulties faced in achieving design throughput rates, maintaining a consistent throughput rate and the inability to achieve design flotation feed particle size distribution while transitioning from partial open pit ore (transitional) treatment to solely underground ore (primary sulphide) treatment. The paper also focuses on the need to run a high ball charge in the primary mill and the damage to the lining system due to this elevated ball charge. The paper also outlines the modelling and simulation work carried out to debottleneck the primary mill. The detailed process modelling identified the presence of elevated proportions of critical size material in ore feed and highlighted the need to include a pebble crusher and primary classifying screen to overcome the problems. Post pebble crusher operational results are also discussed due to the system having been commissioned in February 2015.